What we have achieved so far

Since 2016 when the project began, we have achieved much to improve the highway network and create a safer environment for cyclists and pedestrians within Woking town centre. 

A summary of the works we have completed is below.

  • Created new bus lane and Town Wharf bus stop along Victoria Way.
  • Removed planters and widened Church Path before resurfaced with granite block paving.
  • Created new pedestrian public plaza outside railway station.
  • Relocated the taxi rank to The Broadway.
  • Resurfaced Chapel Street with granite block paving.
  • Rebuilt and resurfaced The Broadway and bus bays with granite block paving.
  • Reconfigured High Street to a one-way bus lane, widened the pedestrian footpath, incorporated a contra-flow cycle lane and resurfaced the highway.
  • Extended High Street and created new junction with Victoria Way.
  • Adapted Goldsworth Road to incorporate new box junction and reconfiguration of junction with Victoria Way.
  • Rebuilt and resurfaced Stanley Road.