Lakeview estate cladding project

We're updating the cladding across 14 medium-rise blocks on the Lakeview estate.

Lakeview estate current phase of work

Our main actions to progress the project over the coming months.

Works contractor

We launched a competitive tender process at the start of 2026 to identify which contractor will carry out the refurbishment work. 

We received bids from 10 different suppliers. After a detailed evaluation of all bids, we have selected a preferred supplier.

Due to the financial value of the contract, appointment of the preferred supplier requires the approval of the Executive. 

Next consultation

Due to the refurbishment project including qualifying works, which will be recharged to leaseholders, a further Section 20 consultation is required before the contract can be awarded.

Leaseholders have been advised of the indicative costs and have until 24 August 2026 to respond to the 30-day consultation.

Council decisions and actions

The appointment of the preferred supplier and the feedback from the Section 20 consultation will be considered by the Executive on 10 September 2026. 

Prior to start-on-site, we will also need to ensure we discharge pre-commencement planning conditions, such as submitting a final landscaping scheme and final colour details/samples and specifications for aluminium panels.

Construction works

Based on this, the programme currently assumes a start date in January 2027. 

Construction is expected to be delivered on a phased, block‑by‑block basis over approximately 30 to 36 months subject to confirming costs, budget and Local Government Reorganisation in Surrey transition.

The refurbishment works are expected to continue beyond the life of Woking Borough Council. The new West Surrey Council will need to demonstrate regulatory compliance in the same way Woking Borough Council does now.