Current works

The current phase of works focuses on the upgrading and resurfacing of a number of key highways, pedestrian footpaths and crossings in the eastern quarter of Woking town centre.

Works to the western end of Church Street East and the horseshoe incorporating Christchurch Way and Chobham Road are already complete.

Information about the remaining elements of this phase of works are outlined below. 

HighwayDetailsConstruction dates
Stanley Road

Full depth reconstruction and resurfacing of highway with granite block paving. Includes pedestrian footpaths.

Full closure of highway in operation.

Complete September 2019
Church Street East (between junctions with Chobham Road and Chertsey Road roundabout)

Full depth reconstruction and resurfacing of highway with granite block paving. Includes pedestrian footpaths.

Temporary one-way traffic lights currently in operation.

Complete November 2019
Victoria Way pedestrian crossing (adjacent to The Lightbox)

Removal of guard rails and resurface crossing island and adjacent pedestrian footpaths with granite block paving.

Pedestrian crossing will remain accessible at all times.

August 2019 to October 2019
Maybury Road (between junctions with Stanley Road and Locke Way)

Widen existing pedestrian footpath to incorporate cycle path, create new pedestrian footpath adjacent to railway line and install raised traffic calming measures.

Temporary traffic lights in operation.

September 2019 to November 2019
Duke Street (between junctions with Chertsey Road and Locke Way)

Widen pedestrian footpath and resurface highway with granite block paving.

Create five disabled parking bays.

September 2019 to November 2019